Media centre / Press releases / BLOCK SIX OF THE ŠOŠTANJ THERMAL POWER PLANT SHUT DOWN AS PLANNED

BLOCK SIX OF THE ŠOŠTANJ THERMAL POWER PLANT SHUT DOWN AS PLANNED

On the evening of Friday, 27 October 2017, Block Six of the Šoštanj Thermal Power Plant will be shut down due to works. By 6 November 2017, once it is synchronised with the network again, an inspection will be performed of a warranty repair that was carried out on Block 6 in June of this year. At the same time, the provider shall eliminate smaller warranty claims and perform all necessary maintenance work. During the shutdown of Block 6 at the Šoštanj Thermal Power Plant, Block 4 will be operational, allowing an uninterrupted supply of electricity.